Sr. Facilities Construction Project Manager, 05/2017 to 11/2021
The University of Texas Health Science Center – Houston, Texas
Client Funded Projects
The University of Texas Health Science Center – Houston, Texas
Client Funded Projects
- CI 1777 - UCT - UTHealth Services Relo 16 to 1
- CI 1782 - UCT - M41 Expansion
- CI 1800 - IMM - 501Q/523 Space Reconfigure – $50k - Converted freezer rooms over to tissue culture labs.
- CI 1801 - IMM - 401M Hood Replacement from 401B
- CI 1808 - Campus - Wellness Centers - Tablet Install
- CI 1810 - IMM - Water Feature Drain Plugs/Covers
- CI 1813 - MSB - Green Stairwell (E) - Wellness Initiative
- CI 1816 - MSB - Risk Assess BSL3 Lab – Worked within multiple BSL3 labs throughout Medical School. This could be combined with several other projects below and would be around $250k altogether. Labs were existing and had to remain operational except for 2-week downtimes allotted each year per lab. This also includes a new autoclave that was replaced in location.
- CI 1817 - MSE - Davit Tie Back Visual Inspection
- CI 1818 - MSB - 3.001 Auditorium Lamp Replacements
- CI 1819 - MSB - 2.221P Security
- CI 1823 - MSB - Lab 2.221P Updates
- CI 1827 - MSB - Room Signage
- CI 1832 - MSB - Willed Body Memorial – Special Memorial that was donated to the school and represents all the individuals that have willed their bodies to research for the UTHealth.
- CI 1836 - IMM - 523 Space Reconfigure to Tissue Culture
- CI 1837 - UCT - 1870 Cube Reconfiguration
- CI 1839 - MSB - 4.0T2 Repurpose to Unisex Restroom
- CI 1840 - MSB - B.301 Crematory
- CI 1844 - UCT - 10th Floor Modifications
- CI 1845 - UCT - Suite 180 Modifications
- CI 1847 - UCT - M45 Modifications
- CI 1849 - UCT - 1000-10 Cube Reconfiguration
- CI 1850 - MSB - Leather Lounge - Electrical Floor Boxes
- CI 1851 - UCT - Cube 1880-10 Reconfigure
- CI 1852 - UCT - New Main Door Suite 1880 West
- CI 1855 - UCT - 1870 Light Relocate
- CI 1858 - UCT - 1565 Cube Reconfiguration
- CI 1860 - MSB - 7.527 Flooring Replacement
- CI 1861 - UCT - 720 BCC Signage
- CI 1862 - UCT - M60 Cube Adjustments
- CI 1864 - UCT - 1510 Office Spaces Reconfigure
- CI 1865 - MSB - Walking Track - Wellness Initiative
- CI 1872 - UCT - 9th Floor Controlled Access
- CI 1887 - IMM - Data Cabling Lab 260
- CIP 1776 - MSB - MSB Reconfigurations – Multiple projects throughout Medical School, new offices, renovation of offices. Approx. $400k
- CI 1869 - CYF - B.106 Conference Room Upgrades
- CI 1870 - OCB - 1.330 EHS Meeting Room Upgrades
- CI 1883 - MSB - 2.116 Office Adjustments
- CI 1885 - UCT - 2200 AV Prep
- CI 1886 - UCT - 9th Floor Cube Adjustments
- CI 1901 - BBS - 1st Floor Lobby Security Desk Signage
- CI 1903 - MSB - Corridor G.4H1 Lighting
- CI 1904 - OCB - 1.160Q Cube Adjustment
- CI 1905 - MSB - BSL3 Interior Camera Conduit Extend
- CI 1910 - MSB - G.300 Sound Proofing
- CI 19102 - MSB - B.210C One Way Mirrors
- CI 1912 - OCB - 2nd Floor Water Station Retrofit
- CI 1913 - CYF - Water Station Retrofit
- CI 1917 - CYF - B.102 Chem Hood Refurb
- CI 1923 - BBS - Suites 4342-4346 Sound Attenuation
- CI 1924 - BBS - UT Physicians Signage Suite 4358
- CI 1931 - IMM - Butterfly Garden – Received the 2019 Awards of Excellence – Silver through the National Association of Landscape Professionals.
- CI 1932 - BBS - 4350-4352 Sound Attenuation
- CI 1934 - UCT - M41/M80/M125 Entrance Signage
- CI 1935 - UCT - M20 Sound Attenuation
- CI 1939 - UCT - 1414 Modifications
- CI 1947 - UCT - 1212 Light Fixture
- CI 1948 - MSB - B.250 B/C Gross Anatomy Cooler/Freezer (ENGR)
- CI 1954 - UCT - Suite M41 Renovations
- CI 1957 - OCB - 1.330 EHS Office Reconfigure
- CI 1959 - UCT - 1105 Ceiling Repair
- CI 1960 - MSB - G.601 Cryo-EM Update
- CI 1962 - MSB - Lab 7.231 Modifications – Renovating existing lab to fit needs of new researcher. Approx. $100k
- CI 1988 - BBS - 1H01/2H.01/3230 Paint
- CIP 1800 - CYF – Decommissioning – Decommission first UTHealth cyclotron along with other radioactive devices being relocated with high security needs. Approx. $900k
- CI 19100 – MSB - LRC G.2H1 Linear Lighting
- CI 19101 - MSB - 50th Anniversary Banner Signs – Requested special privileges from TMC to install 100 banners on their light poles around the UTHealth McGovern Medical School to celebrate the 50th Anniversary of being open.
- CI 19103 - MSB - B.120O Kitchen Counter Replace
- CI 19109 - MSB - LRC Annex B.140 Doors
- CI 19110 - UCT - M40 Sound Attenuation
- CI 19111 - MSB - G.420A Conference Room Update
- CI 19112 - BBS - 3rd Floor Directional Signage
- CI 19114 - UCT - M40 Glass Markerboard
- CI 19115 - JJL - 324/326/328 Door Signage
- CI 19118 - MSB - LRC G.2H1 Ceiling Tiles
- CI 1964 - MSB - Pathology Programming – Programming for Pathology Department throughout Medical School. Approx. $30k
- CI 1973 - CYF - B.110 Vault Reconfigure
- CI 1974 - MSB - Breezeway Glass Repair
- CI 1983 - MSB - G.520 Kitchen Remodel
- CI 1990 - MSB - Lab 5.514 Reconfigure
- CI 1993 - UCT - 1880 Public Affairs Shelving
- CI 1994 - MSB - LRC G.240B Workroom Carpet
- CI 1995 - MSB - B.140 LRC Security Camera
- CI 1998 - BBS - UTP Suite 4358 New Provider Name Add
- CI 2001 - MSB - Lab 7.614 Update
- CI 2004 - BBS - 2.136 Blade Sign
- CI 2005 - MSB - LRC G.250 Storage Cabinet/Freezer
- CI 2010 - MSB - LRC G.240 Linear Bookshelf Light
- CI 2019 - MSB - LRC G.210_G.260 PBL Marker Boards
- CI 2021 - MSB - B.250 B/C Gross Anatomy Cooler/Freezer - ~$100k – Complete conversion of the cooler over to a freezer due to capacity increases for longer term holding.
- CI 2031 - JJL - Suite 324_326_328 Signs
- CI 2036 - MSB - 1.006 Cpt Walkway Replace
- CI 2041 - MSE - R427A Flooring
- CI 2043 - CYF - B100 Flooring Replace
- CI 2045 - MSB - Lab 7.614 Cooler Removal
- CI 2049 - MSB -1006 Wood Floor Refinish
- CI 2052 - MSB - G520G Door Removal
- CI 2054 - MSB - G Yellow RR Grout/Partition Paint
- CI 2056 - MSB - Pathology Design/Engr Assessment
- CI 2071 - MSB - G Yellow Women's RR ADA Hinge
- CIP 1905 - MSB - LRC Student Lounge Conversion – Converted existing LRC space into new student lounge that has won an award and received additional donations to Medical School for excellence in improvement of lounge. Has also been discussed during a TAPPA presentation 2021. Approx. $350k
- CI 2076 - MSB - Bike Rack Camera Upgrades
- CI 2081 - MSB - G601 Emergency Power - ~$200k – Get the Titan Krios Electron Microscope converted to its own ATS and battery back up so that power down times are minimal if not null. The microscope produces money for UTHealth, and downtime had to be mitigated, even during construction.
- CI 2083 - CYF Bldg Wayfinding Sign
- CI 2090 - OCB 1500 Reconfigure
- CI 2095 - OCB 1500 Data
- CI 2101 - MSB B110 Dedicated Circuits
- CI 2102 - MSB G250 Millwork Cabinet
- CI 2103 - MSB Bike Rack Fence Upgrades
- CI 2107 - OCB Relocate EHS Flat Files
- CI 2112 - MSB 7601A BSC Change
- CI 2118 - MSB - G520-550 MSIT Reconfigure
- CI 2119 - MSB - 3020B Pediatrics Chairs Suite Entry Door
- CI 2130 - CYF - Bldg Entry Signage
- CI 2131 - MSB - B120 Office Modifications
- CI 2132 - MSE - R421CDE Lab Reconfigure
- CI 2134 - MSB - 3145 Eqpt Disconnect
- CI 2135 - MSB - 3145 Engr
- CI 2144 - MSB - MSIT G520DEFG Insulation
- CI 2151 - MSB - Bike Rack Loading Dock Upgrades
- CIP 1946 - MSB - 7th Floor Neurology Lab Remodel – Complete gut and renovate with new lab casework for new researcher in Neuro Medical School. Approx. $250k
- CIPS 200 - MSB - 1514 Tissue Culture Lab Conversion – Conversion of existing wet lab into tissue culture lab sectioned off from existing lab. Lab air brought down from 3 floors up. Approx. $150k
- SCI 2100 - MSB - 1514 BSC Requirements
- SCI 2101 - MSB - G550 Dr Tandon Space
- AE 1811 - MSB - Leather Lounge Lighting Modification
- AE 1904 - OCB - 1.110G Warehouse Door/Flaps
- DM 18100 - IMM - Patio Roof Investigation/Repairs
- DM 1813 - CYF - Heat Exchanger Replacement
- DM 1852 - OCB - Main Electrical Service Replacement
- DM 1867 - IMM - Roof Investigation Report/Repairs
- DM 1868 - CYF - Leak Evaluation
- DM 1869 - MSE - Leak Evaluation
- DM 1880 - IMM - 303/304 CT Lab Mechanical Changes
- DM 1883 - MSE - Fire Sprinkler Discharge
- DM 1887 - UCT - Suite 180 Flooring
- DM 1888 - IMM - Room 248 Flooded Drain/Ceiling
- DM 1890 - MSE - Roof Guard Rails
- DMP 1724 - IMM - 907EQ Lighting Upgrades
- DM 18101 - MSE - CLAMC Freezer - 1st Floor – Approx. $100k - Relocate of an animal carcass freezer from 6th Floor to 1st Floor Loading Dock, completely new freezer.
- DM 18103 - MSE - R623 Sprinkler Discharge
- DM 1820 - OCB - (DM 1757) Loading Dock Drainage Modifications
- DM 1881 - MSE - Nexus Valve Replace (4)
- DM 1903 CYF Fire Panel Replacement
- DM 19114 OCB Pest Penetration Mitigation
- DM 1919 - MSE - Replace Domestic Hot Water Generator #2
- DM 1926 IMM Longhorn Lawn Expansion
- DM 1935 (DM 1818) - MSE - Zebra Fish Hot Water Loop
- DM 1953 MSE Clean Steam Gen No. 1 - 5 Yr Maintenance
- DM 1980 - CYF - Normal/Emergency Transformer Replace
- DM 1981 - OCB - Sewer Leak Repairs
- DM 1988 - OCB - Lobby Security Upgrades
- DM 1995 - MSE - Demo 6th Floor CER
- DMP 1982 - MSE - Nexus Valves - Floors 1-3 – Approx. $250k - Renovation of Lab nexus valves, keeping existing labs fully occupied and unimpaired.
- DM 1904-B - MSB - Breezeway Caution Signage
- DM 19115 - CYF - Building Ext Tilt Wall Joint Sealing
- DM 19119 - BBS - Elevator Lobby Directional Signs
- DM 2005 A - MSB - Bldg Sprinkler Adjustments
- DM 20102 - MSE - Vacuum Pump Add
- DM 20104 - OCB - Bldg Break Tank Feasibility
- DM 20113 - UCT - Front Entrance Traffic Control
- DM 20114 - OCB - Foundation Repairs PH1
- DM 20129 - OCB - 1160 Flooring Assessment
- DM 2021 - MSB - Webber Plaza Deck Repairs
- DM 2026 - MSE - Lab Exhaust Rust Proofing
- DM 2095 - MSB - Breezeway Protection Study
- DM 2096 - MSE - Vivarium Cage Wash Exhaust Rust Proofing
- DM 20977 - MSB - Fannin Deck Repairs
- DM 2005-A - MSB - Loading Dock Camera Upgrades
- DM 20116 - MSB - B.4T5/6 RR Auto Openers
- DM 20118 - MSE - Vacuum Pump VFD Add
- DM 20122 - MSB - Breezeway Camera Adjustments
- DM 2103D - OCB - Loading Dock Security Signage
- DM 2103G - MSB - Loading Dock Ramp
- DM 2103I - MSB - Loading Dock Crosswalk
- DM 2122 - MSE - Rabbit Rooms Cooling
- DM 2151 - MSB - Breezeway Repairs
- DMP 2147 - OCB - 1H06 Slab Repairs - ~$500k – Trace and repair a large building sewer leak that was causing the slab to have safety concerns. Ripped out 300 LF of sewer, in an active building’s main corridor within 3 weeks and kept all parties within their locations with minimal disruptions other than route changes.
- DM – MSB/MSE – Exterior Review/Power Wash/Repairs – Approx. $400k – Complete pressure wash and review of the 1M SF across MSB/MSE facades and make sure the buildings were prepared for future storms.
- OM 1800 - UCT - 17th Floor Power Lock
- OM 2100 - OCB - Freezer Farm Signage
- HCYF 1802B - CYF - HH - NFIP – Building
- HIMM 1801B - IMM - HH - Leaks – Building
- HMSE 1801B - MSE - HH - Leaks – Building
- LR8SPH1 - SPH - Risk/Threat Assess
- LR 2002 - OCB - AHU 8/9 (DMP 1930) – $1.2M – Repair two air handlers that had to keep the older units active until the new units could be transferred over to and reduce downtime. One AHU received a completely revised location to reduce future leaks and needed a mechanical area built out.
- LR – MSE – Tunnel Wash Replacement – Approx. $900k - Complete replacement of 20-year-old tunnel wash in existing lab space.
- TMSB 1606 - MSB - 3.001 Auditorium Lamp/Ballasts Remaining
- TMSB 1606 - MSB - MSB Breezeway CCTV Replacement
- TMSB 1701 - MSB - Roof Guard Rails
- TUCT 1606 B17 - UCT - 988B Gen Load Bank
- TMSB 1804 - MSB - Accreditation Interior Refresh – Necessary for accreditation walks of the school to be looking best and ready for review. Approx. $100k
- TMSB 1804 - MSB - Yellow Restroom Upgrade
- TMSB 1904 – MSB – Indoor Air Quality Renovations – Office/Corridor Areas of 7 floors that involved relocating people to temp offices and completing a phase in 6 weeks and returning them and their furniture back to the revamped areas/offices. Approx. $10M